Review of Current Work Status

Brussels| After one year of active project work of the BECA partners, the progress was reviewed during a first review meeting in Brussels from 22nd to 23rd of February 2012. This first year was mostly spent to design the most efficient system for each pilot site. This was done by taking into account not only the technical specificities of the solutions, but also the profile and requirements of the tenants. With the end of the first year, several work packages have been ended :

 

WP1 : The needs of the end users (tenants and housing companies) have been defined, The existing experiences and legal constraints have been collected.

WP 2 : Service processes have been designed, in terms of actors, tasks and documents

WP 3 : The system architecture and specifications has been elaborated.